HELSINGIN SANOMAT
  INTERNATIONAL EDITION - BUSINESS & FINANCE

   You arrived here at 07:30 Helsinki time Friday 25.5.2012

   HOME

   ARCHIVE

   ABOUT



   SUOMEKSI -
   IN FINNISH






Massive compensation sought for delays in construction of Olkiluoto III nuclear reactor

TVO announces further rollback of plant opening


Massive compensation sought for delays in construction of Olkiluoto III nuclear reactor
 print this
Yet another delay has been announced in the construction schedule of the Olkiluoto III nuclear reactor.
      The installation was originally supposed to be up and running in 2009, but the date has been pushed back numerous times.
      The reason for the latest delay was problems in the planned automation system.
      Teollisuuden Voima (TVO) announced on Wednesday that the third reactor at the Olkiluoto site - the fifth commercial nuclear reactor in Finland - will not be ready to go onstream and generate electricity until 2014.
      According to Jouni Silvennoinen, the head of the project, TVO has demanded compensation from the builder Areva-Siemens amounting to more than a billion euros.
     
The Finnish construction industry journal Rakennuslehti has previously noted that the German company has reported in connection with the publication of its results that TVO has previously said that it is entitled to compensation worth EUR 2.4 billion from the Siemens-Areva consortium.
      Meanwhile, the consortium says in turn that it is owed about a billion euros by TVO.
      TVO has informed the Nordic Electricity Exchange that electricity from the third unit of Olkiluoto would not be on the market in 2013.
      According to Silvennoinen, the delay will not cause any electricity shortages in Finland.
      Finland is an importer of electricity, and the purpose of Olkiluoto III will be to replace electricity imports and coal-fired power plants.
     
The new reactor was ordered on a turnkey basis, and the builder is responsible for keeping to the schedule.
      The investment costs of the 1,600 MWe plant were originally estimated at EUR 3.5 billion.
      “Time has passed and money has been spent”, Silvennoinen says.
      Ten billion?
      “No comment.”
     


Previously in HS International Edition:
  Construction work on Olkiluoto III nuclear reactor to experience further major delays (20.4.2010)
  Date of completion for Olkiluoto III nuclear plant still anybody´s guess (19.10.2009)

See also:
  Green League would close down nuclear power plants in Olkiluoto in 2018 (19.9.2011)
  Costs of delay in construction of Olkiluoto III approaching price of new reactor (29.1.2009)
  TVO seeks EUR 2.4 billion in damages for Olkiluoto nuclear reactor delays (28.1.2009)

Links:
  Olkiluoto III (TVO)
  Nuclear Power in Finland (Wikipedia)

Helsingin Sanomat


  13.10.2011 - TODAY
 Massive compensation sought for delays in construction of Olkiluoto III nuclear reactor

Back to Top ^